Primavera P6 Duration Types

Oracle Primavera P6 Duration Types Explained

How to calculate duration in Primavera P6? Duration types and percent complete types have effects on remaining activity duration, resource, and cost distribution when progressing the schedule in Primavera P6. Basically, activity durations control the critical path and the completion date of a project. Activity duration type also affects the activity remaining duration and completion date when progressing the schedule with updates.


Before to start creating a project schedule, it is a good idea to understand the activity duration types and their effects on the work schedule. Basically, four duration types are available in Oracle Primavera P6. Choosing the most suitable duration type depends on your project requirements,  project type, and tracking method.

In this article, we will review the Oracle Primavera P6 duration types and their effects considering the physical percent complete type.

How to Calculate Duration in Primavera P6?

Duration types are used to estimate the activity completion date in Primavera P6. Resource availability, costs, and deadlines are important factors for selecting the most suitable duration type.

Note that, duration type applies only when you have resources assigned to the activity.

Below are the duration types of Primavera P6.

  • Fixed Duration & Units/Time or Fixed Duration & Units
  • Fixed Units/Time
  • Fixed Units

How to Use Oracle Primavera P6 Duration Types?




For better understanding, let’s take a look at the example below.

The figure below (Figure 1) shows a sample project. As shown in the below figure, three welding activities are in parallel and the percent complete type is “Physical”. They will be performed in three different locations but at the same time.

Figure 1 Sample Project -how to calculate duration in primavera p6

Figure 1 Sample Project- P6 Duration Types

In order to analyze the effect of different duration types, select the duration type of each activity as below, Figure 2.

Figure 2 Duration Types

Figure 2 Duration Types-  P6 Duration Types

Let’s assume that the Budgeted labor unit of each activity is 1000 Manhour.

Fixed Duration and Units/Time

Resource quantities do not affect the activity completion time because the activity duration is fixed. Let’s assume that the Activity A1040 Welding Between KP 50 – KP 100 started on 18-May-18 and %80 of it is completed physically. The remaining duration of the activity is 25 days. When we enter the remaining duration we see that the actual and the remaining labor unit is 500 Manhour as shown in Figure 3.

Figure 3 Fixed Duration and Units Time

Figure 3 Fixed Duration and Units Time- P6 Duration Types

We want Primavera P6 to calculate that the actual unit is %80 of 1000 Manhour because %80 of work has been completed. Therefore we entered 800 Actual Manhour and saw that the At Completion Units become 1300 Manhour as shown in Figure 4.

Figure 4 Fixed Duration and Units Time Change

Figure 4 Fixed Duration and Units Time Change-Oracle Primavera P6 Duration Types

In the Fixed Duration and Units/Time duration type, remaining units and remaining units/time remain constant. At completion units and costs increases as the actual units increase because the units are not fixed.

Fixed Duration and Units

We assume that the Activity A1050 Welding Between KP 100 – KP 150 started on 18-May-18 and %80 of it is completed physically. The remaining duration of the activity is 25 days. When we enter the remaining duration we see that the actual and the remaining labor unit is 500 Manhour in Figure 5.

Figure 5 Fixed Duration and Units

Figure 5 Fixed Duration and Units-Oracle Primavera P6 Duration Types

We entered 800 Actual Manhour and saw that the At Completion Units didn’t change. Only the Remaining Units have changed as shown in Figure 6.

Figure 6 Fixed Duration and Units Changes

Figure 6 Fixed Duration and Units Changes-Primavera P6 Duration Types

In the Fixed Duration and Units duration type, remaining units and remaining units/time remain changes. At completion units and costs remain constant as the actual units increase because the units are fixed.

Fixed Units




The budgeted unit (or budgeted cost) is a limiting factor in this duration type. We assume that the Activity A1050 Welding Between KP 0 – KP 50 started on 18-May-18 and %80 of it is completed physically. The remaining duration of the activity is 25 days. When we enter the remaining duration we see that the actual and the remaining labor unit didn’t change as shown in Figure 7.

Figure 7 Fixed Unit

Figure 7 Fixed Unit

We entered 800 Actual Manhour and saw that the Remaining Units and At Completion Units didn’t change. Only the Remaining Units/Time has changed but the activity duration is compressed as shown in Figure 8.

Figure 8

Figure 8

Activity duration changes when you update the work schedule.

Updating the Project Schedule

The figure below (Figure 9) shows the updated work schedule after moving the data date forward 70 days and recalculating the schedule.

how to calculate duration in primavera p6

As shown in the figure, the remaining duration of the activities (A1040, A1050) with fixed durations didn’t change. The remaining duration of the activity A1060 has changed.

Summary




Oracle Primavera P6 duration types determine the activity completion time and activity completion time affects the project duration. It determines whether the schedule, resource availability, or costs are most important when updating activities. The duration type applies only when you have resources assigned to the activity [1]. If the duration type is not properly set, undesired effects and problems will occur during the updating phase. Fixed duration and units are the most common duration type for progressing the schedule. Other duration types can also be used based on your project requirements. Note that this is an important concept in Oracle Primavera P6 training. Therefore, you need to know how to calculate duration in Primavera P6 in order to create a serviceable baseline schedule.

References 

[1] docs.oracle.com

See Also

Primavera P6 Download

Tags:
5 Comments
  1. Avatar for mink lashes birmingham
    mink lashes birmingham 6 years ago

    I got what you intend, regards for putting up. Woh I am pleased to find this website through google.

  2. Avatar for promise rings cheap
    promise rings cheap 6 years ago

    Hi there everyone, it’s my first visit at this website, and article is truly fruitful designed for me, keep up posting these articles.

  3. Avatar for onesie pajamas
    onesie pajamas 6 years ago

    This post is invaluable. When can I find out more?

  4. Avatar for wastewater treatment methods
    wastewater treatment methods 6 years ago

    Thank you for some other fantastic post. Where else could anybody get that kind of info in such a perfect method of writing? I have a presentation subsequent week, and I am on the search for such info.

  5. Avatar for video games rot your brain
    video games rot your brain 5 years ago

    Saved as a favorite, I really like your blog!

Leave a reply

Your email address will not be published. Required fields are marked *

*

ALL TOPICS

Log in with your credentials

Forgot your details?