Precedence Diagramming Method Example

Precedence Diagramming Method Example
Precedence Diagramming Method Example

Precedence Diagramming Method Example

Precedence Diagramming Method (PDM) is a visual representation technique which is used to prepare the project schedule network diagrams and determine the critical path.
The main advantage of Precedence Diagramming Method (PDM) is that it demonstrates the activity relationships. This article reviews a Precedence Diagramming Method Example and analyzes the basics of it.



It is critical for a project manager to realise the activity relationships because it is important while preparing the network diagram and then creating the project schedule.

For better understanding, let’s analyze the example below and follow the steps.

Precedence Diagramming Method (PDM) Example
Precedence Diagramming Method (PDM) Example

İn this example A,B,C,D,F,G,H,I are the activities. Numbers above the boxes are the durations. Activity B is a predecessor activity that logically comes before a dependent activity F in this network system. Activity F is a successor activity is a dependent activity that logically comes after the Activity F. There is a F-S Relationship between activity B and F.

Step 1 : PDM Forward Pass Calculation



Forward Pass Calculations specify the minimum dates at which each activity can be performed and, ultimately, the minimum duration of a project.

Precedence Diagramming Method (PDM) Forward Pass Calculation
Precedence Diagramming Method (PDM) Forward Pass Calculation

Step 2 : PDM Backward Pass Calculation



Backward Pass Calculations determine the latest dates by which each activity can be performed without increasing the projects minimum duration.

Precedence Diagramming Method (PDM) Backward Pass Calculation
Precedence Diagramming Method (PDM) Backward Pass Calculation

Step 3 : PDM Float Calculation for Each Activity



Precedence Diagramming Method (PDM) Float Calculation
Precedence Diagramming Method (PDM) Float Calculation

Total float is the amount of time that an activity can be delayed without delaying the project completion date. Total float is 0 on the critical path.

Total Float: LS – ES = 17-7 = 10
Total Float: LF – EF = 27-17 = 10

Total float can be calculated by subtracting the Early Start date of an activity from its Late Start date or Early Finish date from its Late Finish date.

Step 4 : PDM Identifying the critical path



Precedence Diagramming Method (PDM) Critical Path
Precedence Diagramming Method (PDM) Critical Path

When we analyze the network diagram we will see that there are some paths and every path have duration.
The critical path is the longest path in the network diagram and total float of critical path is zero.

Summary



In this article we review a Precedence Diagramming Method Example. In this simple example we show how to make forward, backward, total float and critical path calculation. The Precedence Diagramming Method (PDM) enables us to make these calculations correctly. By the help of softwares it is very easy to make these calculations.

See Also: Precedence Diagramming Method in Scheduling

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.