PERT Method – Program Evaluation and Review Technique Example & Definition

Pert Method

Project managers often use graphical representation tools to understand their projects’ performance. CPM, Gantt, and PERT Charts are used to demonstrate workflow and sequence of activities. Although both scheduling tools serve the same purpose, they are different from each other. In this article, we will discuss the PERT definition and demonstrate how to use PERT Method with the help of an example.

PERT VS CPM

The PERT Method (or Program Evaluation and Review Technique) is one of the most common scheduling techniques for network analysis which is used to track and coordinate complex tasks in a project. Similar to the CPM Method, PERT helps to analyze the project work schedule by focusing on each task and calculating the minimum time required to complete the project.

Although both of them use a common approach for preparing the network and determining its critical path, PERT focuses on probabilistic elements for task duration estimation, while CPM deals with low uncertainty in task durations.

What is the PERT defınıtıon? (Program Evaluation and Review Technique)

PERT Method (Program Evaluation and Review Technique) was first developed by the US Navy SPO (Special Projects Office) in 1967 during the Polaris missile development program then it was applied to the other industries. Both CPM and PERT are complementary tools and they are developed at roughly the same time.

Unlike other methods, PERT is an event-oriented technique that uses three-time estimates (optimistic, expected, and pessimistic) for each task. With this aspect, it employs uncertainty while calculating the task durations. These characteristics make the Program Evaluation and Review Technique useful for large-scale, complex, and non-routine projects.

The WBS (Work Breakdown Structure) concept which divides the scope into manageable sections was developed in conjunction with PERT .

Why Would You Use a PERT Chart?

One of the most important responsibilities of a project manager is making correct estimations. Since projects are full of uncertainties, it is often difficult for a project manager to foresee what will happen tomorrow. Besides, project sponsors and key project stakeholders never like uncertainty regarding project costs and milestone dates.

The project manager’s role and responsibilities include reducing and mitigating negative project risks as well as increasing the possibility of opportunities.

Project managers should use PERT charts in conjunction with other tools and techniques if they need more accurate and forecasts. Because PERT Chart employs three time estimations to provide you an average result.

Pert Vs Cpm Method, Differences Between Pert And Cpm Method

Key Differences Between the PERT and cpm Method

Below are some key differences between the PERT and CPM Method (Critical Path Method)

  • In the Critical Path Method activity durations are well defined but in PERT, time estimations are uncertain.
  •  The Critical Path Method is a method of control of time and costs, however, PERT is a technique of planning and control of time.
  • There are three estimates in PERT such as optimistic, pessimistic, and most likely. In the Critical Path Method, there is only one estimate.
  • In PERT Chart, only FS relationship type is applicable. In CPM Chart 4 relationship types (FS,SS,SF,FF) can be applicable.
  • PERT Chart is event-oriented however, CPM Chart is start and completion oriented.
  • PERT is more applicable to research and development projects rather than CPM.

PERT Chart vs Gantt Chart

Both PERT charts and Gantt charts serve as visual aids for project planning, they differ in their applications.

PERT charts, as explained above, were designed to streamline the planning and scheduling of extensive and sophisticated projects. Conversely, Gantt charts are another graphical representation used to plan and schedule projects, dissecting project scope into tasks displayed on a timeline. A Gantt chart facilitates the construction of project timelines, establishment of task dependencies, and visualization of each task’s duration.

PERT Analysis Formula

Pert Method Formula

The PERT method employs simple statistic calculations. It uses three-time estimations.

  • Optimistic Estimate: The shortest time required to complete the task.
  • Pessimistic Estimate: The longest time required to complete the task.
  • Most Likely Estimate: The most possible time (probable duration) required to complete the task.

Expected time is calculated with the help of the PERT Analysis formula below

Expected time = ( Optimistic + 4 x Most likely + Pessimistic) / 6

Pert Method Estimating The Time Disribution

Image Source: U.S. Department of the Navy, Program Evaluation Research Task, Summary Report

The PERT Method Implementation Steps

Track the following steps while creating a PERT Chart;

1. List the activities and milestones

The first step is to determine the tasks required to complete the project.

2. Determine the sequence of activities

The second step is to determine the order of the activities. Which activity is the predecessor which one is the successor? It is easy to determine the sequence of some activities however the sequence of some tasks may require deep analysis.

3. Build a network diagram

The third step is to create the network diagram with the help of software or by hand and place the activities on the diagram.

4. Estimate the activity durations

The PERT Method uses three duration estimates for activities which are;

  • Optimistic Estimate
  • Pessimistic Estimate
  • Most Likely Estimate

With the help of three estimates, expected duration is calculated.

5. Determine the critical path

The critical path is the longest path of the network diagram. Forward and backward pass calculations is used to determine the critical path.

The PERT Method Example

We discussed the PERT Definition and how it differs from CPM. Now we will provide a simple PERT Method example with the solution.

In the following example, you are a project manager of a power plant project. You tracked the steps mentioned above and listed the following inputs;

  • All the Activities
  • Predecessors
  • Optimistic, Pessimistic, and Most Likely Activity Durations
    By using “The Pert Formula = (To + 4Tm + Tp)/6”, you calculated the expected duration for each activity.
    All the inputs are listed in the table below.
Program Evaluation And Review Technique Example - Pert Chart
Pert – Program Evaluation And Review Technique Example

After building a network diagram and estimating the activity durations, you will determine the critical path by making forward and backward pass calculations.
Forward Pass Calculations specify the minimum dates at which each activity can be performed and, ultimately, the minimum duration of a project.

Forward Pass Calculation Program Evaluation And Review Technique
Pert -Forward Pass Calculation

Backward Pass Calculations of Program Evaluation and Review Technique determine the latest dates by which each activity can be performed without increasing the project’s minimum duration.

Pert Method Backward Pass Calculation
Pert -Backward Pass Calculation

After completing the backward pass calculation, you can easily determine the critical path. In project management, “float” or “slack” is the amount of time that a task can be delayed without affecting the deadlines of other subsequent tasks, or the project’s final delivery date. Total float/slack is 0 on the critical path.

Pert Method -Activity

Total Float: LS – ES = 18-15 = 3
Total Float: LF – EF = 30-27 = 3

The total float can be calculated by subtracting the Early Start date of an activity from its Late Start date or Early Finish date from its Late Finish date.

Pert Method -Critical Path - Pert Chart Example Program Evaluation And Review Technique
 

When we analyze the network diagram we will see that there are some paths and every path have duration.
The critical path is the longest path in the network diagram and the total float of the critical path is zero.

Summary

In real life, projects are not executed as it was planned all the time. Risks, unexpected events, uncertainty, and subjective estimates are significant reasons for deviations. PERT Chart is helpful for estimating the project completion time in case of uncertainty. However, it may be difficult to use without software.

In this example, we talked about the PERT definition and calculated the expected duration for each activity and anayzed the difference between PERT and CPM. By making forward, backward calculations, we determined the critical path. Accuracy of expected durations that affect the critical path depends on the optimistic, pessimistic, and most likely duration estimates. With the help of PERT Chart software, it is easy to make these calculations efficiently for many combinations.

Related posts


6 thoughts on “PERT Method – Program Evaluation and Review Technique Example & Definition”

  1. Excellent description.
    I have a problem in that suppose, we have only the optimistic and the pessimistic times. The most likely times are not given. In such case can I take the average of the two as the expected time.
    2ndly suppose it is given that the time of an activity follows a normal distribution with a mean m and sigma of s; how do we proceed.
    Thanks and regards
    virendra

    Reply
  2. Great explanation of the PERT method! I appreciate the detailed examples that help clarify how to apply it in real projects. It’s a valuable tool for project management, and your insights have made it much easier to understand. Thanks for sharing!

    Reply

Leave a Comment